We have a bulletin from Higgins Construction about the A2 Dominion site on the Edgware Road – that’s the site beside the MS Society offices – here.
Key dates include:
- concrete frames complete in November and December 2016
- tower cranes removed in Spring 2017
- hand-over to client in May 2018